Step 4 · Sell

See what it sells for

Price, fill and contract terms, as scenarios.

Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Sweden

Data centres in Sweden

At a glance: Sweden

Pipeline projects
13
6 permitted or being built
Checked 17 Oct 2026
New grid connections
Congested
All kapacitet för uttag är för närvarande tilldelad. Stockholm, transmission
Checked 23 Oct 2026
Wholesale power price
43€/MWh
Day-ahead, 2025 mean, Sweden
Calendar year 2025
Grid carbon intensity
35g CO₂/kWh
Yearly average, Sweden
Latest full year
Next national rule date
1 Jan 2027
Proposed entry into force of Sweden’s draft law on cost-benefit analysis and waste heat use for data centres above 1 MW
Applies in Sweden
Latency to nearest major hub
12 ms
Round trip, Stockholm to Amsterdam
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 13 data-centre projects in Sweden, and 6 of them are permitted or being built.

Data centres in Sweden in October 2026

The tracker follows 13 data centre projects of 1 MW or more in Sweden, 6 of them permitted or being built. 8 developers are behind them, led by EcoDataCenter (4), atNorth (2) and Google (2).

Projects by stage

  • Announced 4
  • In planning 3
  • Permitted 1
  • Contractor appointed 1
  • Under construction 4

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 1
  • Facility, campus or unstated basis 7
  • First phase only 2
  • No capacity published 3

Each capacity is on its own stated basis; never added.

Who is building in Sweden

A joint venture counts once per partner. All operators and developers.

What changed

5 milestones in the last 90 days; the newest is from Oct 2026.

Power and grid in Sweden

Congested

New grid connections are congested (Stockholm, transmission). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
35g CO₂/kWh
2nd cleanest of 30 countries; 99% renewable or nuclear
Business electricity price, latest full year
89€/MWh
3rd cheapest of 26; wholesale is 66% of it
Wholesale power, 2025 average
43€/MWh
2nd cheapest of 30

Climate at Stockholm

Hours a year above 27 °C dry-bulb
13h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
0h
worst year 0 h
Hours a year above 20 °C wet-bulb
39h
limit for evaporative cooling

Hourly reanalysis at the city’s grid cell, 2016 to 2025.

Annual averages are national, for the latest full year.

Fibre latency from Stockholm

Round trips from Stockholm
ToRound trip, minimumPath lengthPath
Helsinki3.9 ms396 kmStraight line (no mapped land route)
Oslo4.3 ms438 kmMapped fibre route
Copenhagen5.6 ms573 kmMapped fibre route
Amsterdam12 ms1,261 kmMapped fibre route
Frankfurt13 ms1,292 kmMapped fibre route
London16 ms1,669 kmMapped fibre route
Paris17 ms1,707 kmMapped fibre route
Dublin19 ms1,950 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 1 Jan 2027proposed entry into force of Sweden’s draft law on cost-benefit analysis and waste heat use for data centres above 1 MW, if it is adopted
  3. 15 May 2027EU database and French reports due (every year)
  4. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Sweden.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 6 official bodies, checked 23 October 2026: Copernicus Climate Change Service (ERA5), EUR-Lex (Official Journal of the EU), Sollefteå kommun, Svenska kraftnät, Timrå kommun, Vattenfall Eldistribution.