Markets / Operators / atNorth

atNorth data centre projects in Europe

Projects tracked
7
of 1 MW or more
Permitted or being built
4
3 at announcement stage
Countries
4
with at least one project
Milestones, last 90 days
4
newest Oct 2026

As of (newest check)

Our European pipeline tracker follows 7 data-centre projects of 1 MW or more that atNorth develops or co-develops, in 4 countries; 4 are permitted or already being built. The largest share is in Finland, with 3 projects.

57% are permitted or being built, against 44% across the whole tracker, so the pipeline is further along than the European average. The milestones we hold run from Jan 2026 to Oct 2026.

Projects by stage

  • Announced 3
  • Permitted 2
  • Under construction 2

What the capacity figures measure

  • Facility, campus or unstated basis 4
  • First phase only 3

Stated size, where a figure is published

  • 20 to 49 MW 2
  • 50 to 99 MW 1
  • 100 to 249 MW 1
  • 250 MW and above 3

Bands mix bases, so read them as orders of size; never added.

Where atNorth is building

Latest milestones

The newest 4 steps we recorded, by market and stage.

  1. Oct 2026DenmarkPermitted
  2. Oct 2026Finland Project announcedAnnounced
  3. Oct 2026SwedenPermitted
  4. Jul 2026Finland YIT signed a design-and-build contract of about EUR 300 millionUnder construction
Method

Projects of 1 MW or more (or unstated), announced to under construction, that we have found and checked.

  • Projects atNorth develops or co-develops; a joint venture counts once per partner.
  • Capacities are on different bases: counted, never added.
  • From public filings and announcements; DC Blueprint is independent of atNorth. No project is listed.

Cite as: DC Blueprint, “atNorth data centre projects in Europe”, https://dcblueprint.com/sell/operators/atnorth (checked 17 Oct 2026). © DC Blueprint.