Step 1 · Plan

Build your multi-year plan

Site, grid, costs, revenue and returns in one case.

Project Data centre, Frankfurt Frankfurt, 20 MW, 2 phases

Example values. Change any of them and they become your project, kept in this browser. Create a free account to keep it

Data centre, Frankfurt: 20 MW of IT in one building of 4 halls (16,710 m²), a 31 MVA connection, first hall ready May 2030. Cost and returns are in Premium.

Site and market

1 of 7
Starting point
Land
Phases
Phase 1 Year 0 MW
Phase 2 yrs MW
Development cost Premium
Project IRR Premium Unlevered, pre-tax
NPV Premium At a 10.0% hurdle
Payback – Not before the exit
First hall ready May 2030 Set by long-lead equipment
Risk level Low 0 high, 2 medium
IT capacity 20 MW 2,500 racks
Gross floor area 16,700 m² 4.1 ha site
Grid connection 31 MVA 29.2 MW peak
Monthly revenue Premium Stabilised, today’s money

Programme

  • Pre-application: Oct 2026 to Apr 2027
  • Planning and permits: Apr 2027 to Nov 2027
  • Long-lead equipment: Nov 2027 to Aug 2029, sets the date
  • Construction, phase 1: Jun 2028 to Feb 2030
  • Commissioning and handover: Feb 2030 to May 2030, sets the date
  • Phase 2, 10.0 MW: Jun 2031 to May 2033
First hall ready May 2030: long-lead equipment sets the date (red). Reserving transformers and generators before permits (Construction step) moves the date.

Reference data for the site and the grid

Live and monthly grid data, the power plant map, siting costs, market comparison and fibre latency, each with its sources and dates.

Grid and power

Siting and markets