Markets / Grid connection tracker
Grid connection tracker
Where Europe’s grid can still connect a data centre
On 23 October 2026 the tracker covers 17 countries: 11 pause, ration or condition new grid connections in all or part of their grid, 2 report congestion without a formal rule, and 4 have none of these in force.
At a glance
- Pause, ration or condition new connections
- 11
- of 17 countries
- Grid connection tracker,
- New connections paused nationwide
- United Kingdom
- 1 of 17
- Grid connection tracker,
- Most data-centre load waiting to connect
- Italy
- 94.0 GW
- Grid connection tracker, figure of
Coverage and quality
What is included
17 countries and 15 hubs. A restriction shows only when a rule in force pauses, rations or conditions new connections, or the grid is declared full.
What is not covered
Other countries, single-site offers and enquiry volumes. 8 of the 17 countries publish no data-centre pipeline figure.
Units
MW or GW. 23 of 128 power figures were published in MVA or GVA and are read as MW, original unit shown.
Corrections
Data © DC Blueprint. Each row shows the date its sources were last checked.
Where new data-centre load can still connect
Shade: the strictest rule on new connections. Bubble: data-centre load waiting to connect.
Europe now
Strictest rule first
- 1 United KingdomLondon Paused 73.0 GW
- 2 NorwayOslo Paused in parts 4.2 GW
- 3 DenmarkCopenhagen Rationed Not published
- 4 GermanyFrankfurt, Berlin Rationed Not published
- 5 Portugal Rationed Not published
- 6 SpainMadrid Rationed in parts 6.3 GW
- 7 NetherlandsAmsterdam Rationed in parts Not published
- 8 IrelandDublin Conditional 2.0 GW
- 9 Belgium Conditional Not published
- 10 FinlandHelsinki Conditional in parts Almost 5.0 GW
- 11 CzechiaPrague Conditional in parts Not published
- 12 PolandWarsaw Congested Not published
- 13 SwedenStockholm Congested in parts 7.3 GW
- 14 Italy None in force 94.0 GW
- 15 FranceParis, Marseille None in force 18.0 GW
- 16 Austria None in force 2.5 GW
- 17 SwitzerlandZurich None in force Not published
Grid connections by country
Rules in force, data-centre pipeline and published wait, per country.
| Market | New connections | Data-centre pipeline | Stage | Trend | Wait |
|---|---|---|---|---|---|
| United Kingdom London Checked 23 Oct 2026 | PausedTransmission, all customers | 73.0 GWNational, Mar 2026Filed, checked 11 Oct 2026 | Queued | No earlier figure | Not published, checked 23 Oct 2026 |
| Germany Frankfurt, Berlin Checked 23 Oct 2026 | RationedTransmission, large loadsPaused in partsBerlin, distribution, large loadsRationed in partsBerlin, distribution, large loads | Not published, checked 23 Oct 2026 | 2030–2036Earliest connection, in partsFiled, checked 11 Oct 2026 | ||
| Netherlands Amsterdam Checked 12 Oct 2026 | Rationed in partsAmsterdam, all voltages, data centresConditional in partsAmsterdam, distribution, data centresCongested in partsAmsterdam, transmission, all customers | Not published, checked 12 Oct 2026 | 2034–2037Earliest connection, AmsterdamFiled, checked 11 Oct 2026 | ||
| France Paris, Marseille Checked 11 Oct 2026 | None in forceNo pause, cap or condition published | 18.0 GWNational, May 2026Filed, checked 11 Oct 2026 | Reserved | ↑ from 5.0 GWDec 2024 | 2028–2029Earliest connection, selected sitesFiled, checked 11 Oct 2026 |
| Ireland Dublin Checked 23 Oct 2026 | ConditionalAll voltages, data centresPaused in partsDublin, transmission, data centres | 2.0 GWNational, May 2026Filed, checked 11 Oct 2026 | Contracted | No earlier figure | Not published, checked 23 Oct 2026 |
| Austria Checked 23 Oct 2026 | None in forceNo pause, cap or condition published | 2.5 GWNational, Apr 2026Filed, checked 11 Oct 2026 | Requested | No earlier figure | Not published, checked 23 Oct 2026 |
| Belgium Checked 23 Oct 2026 | ConditionalTransmission, all customersConditional in partsDistribution, large loadsCongested in partsDistribution, large loads | Not published, checked 23 Oct 2026 | Not published, checked 23 Oct 2026 | ||
| Czechia Prague Checked 23 Oct 2026 | Conditional in partsPrague, distribution, all customers | Not published, checked 23 Oct 2026 | 5–15 yearsTypical waitFiled, checked 11 Oct 2026 | ||
| Denmark Copenhagen Checked 23 Oct 2026 | RationedTransmission, large loadsConditionalTransmission, large loadsRationed in partsCopenhagen, distribution, large loads | Not published, checked 23 Oct 2026 | 5–10 yearsTypical waitFiled, checked 11 Oct 2026 | ||
| Finland Helsinki Checked 11 Oct 2026 | Conditional in partsHelsinki, distribution, large loads | Almost 5.0 GWNational, Aug 2026Filed, checked 23 Oct 2026 | Contracted | ↑ from over 3.0 GWJun 2026 | Not published, checked 11 Oct 2026 |
| Italy Checked 23 Oct 2026 | None in forceNo pause, cap or condition published | 94.0 GWNational, Jun 2026Filed, checked 11 Oct 2026 | Queued | ↑ from 78.8 GWJan 2026 | Not published, checked 23 Oct 2026 |
| Norway Oslo Checked 11 Oct 2026 | Paused in partsTransmission, large loads | 4.2 GWNational, Oct 2026Filed, checked 11 Oct 2026 | Reserved | No earlier figure | Not published, checked 11 Oct 2026 |
| Poland Warsaw Checked 11 Oct 2026 | CongestedTransmission, all customersPaused in partsTransmission, all customers | Not published, checked 11 Oct 2026 | Not published, checked 11 Oct 2026 | ||
| Portugal Checked 23 Oct 2026 | RationedAll voltages, large loads | Not published, checked 23 Oct 2026 | Not published, checked 23 Oct 2026 | ||
| Spain Madrid Checked 11 Oct 2026 | Rationed in partsTransmission, all customers | 6.3 GWNational, Oct 2026Filed, checked 11 Oct 2026 | Granted | No earlier figure | Not published, checked 11 Oct 2026 |
| Sweden Stockholm Checked 11 Oct 2026 | Congested in partsStockholm, transmission, all customers | 7.3 GWNational, Oct 2026Filed, checked 11 Oct 2026 | Queued | No earlier figure | 1–5 yearsTypical wait, in partsFiled, checked 11 Oct 2026 |
| Switzerland Zurich Checked 11 Oct 2026 | None in forceNo pause, cap or condition published | Not published, checked 11 Oct 2026 | 3–10 yearsTypical waitFiled, checked 11 Oct 2026 | ||
- Unit
- Status of new connections, by country and voltage level
- Coverage
- 32 markets in 17 countries
- Last check
- 23 October 2026
- Basis
- 274 filed by an operator, regulator or ministry, 4 forecasts or planned capacity, 3 metered
- Review due
- monthly where connections are paused or rationed, every two months where conditional, quarterly elsewhere; next 22 November 2026
Method
A country shows a restriction only when a rule in force pauses, rations or conditions new connections, or the grid is declared full; the worst rule at either voltage level sets its status. Pipeline figures count data-centre load alone, at the stage stated, and are never added across countries.
Sources: 58 official bodies, checked 23 October 2026
50Hertz, ACM (Dutch regulator), Amprion, Austrian Power Grid (APG), BOE (Spanish official gazette), Bundesnetzagentur, Camera dei deputati, Canton of Zurich, Caruna, Central Statistics Office (Ireland), City of Frankfurt am Main, CRE (French regulator), CREG (Belgian regulator), CRU (Irish regulator), Danish Ministry of Climate, Energy and Utilities, Department for Energy Security and Net Zero, DGEG (Portuguese energy directorate), Dziennik Ustaw (Polish official journal), EirGrid, Elvia, Energinet, ERÚ (Czech energy regulator), EUR-Lex (Official Journal of the EU), Fingrid, Fluvius, Gemeente Amsterdam, Gemeente Haarlemmermeer, German Federal Ministry for Digital Affairs, Government of Portugal, Helen Sähköverkko, Hessian Ministry for Digital Affairs, Liander, London Assembly Planning and Regeneration Committee, MITECO, MITNETZ STROM, NESO, Netbeheer Nederland, Netztransparenz (German TSOs), NRM Netzdienste Rhein-Main, Officiële bekendmakingen (Dutch official gazette), Ofgem, ORES, PSE, Radius Elnet, Red Eléctrica, REN, Retsinformation (Danish law), RIS (Austrian federal law), RTE, Statnett, Stromnetz Berlin, Svenska kraftnät, Swissgrid, TenneT, Terna, TransnetBW, Vattenfall Eldistribution, ČEPS.