Markets / Operators / EcoDataCenter

EcoDataCenter data centre projects in Europe

Projects tracked
4
of 1 MW or more
Permitted or being built
2
none at announcement stage
Countries
1
with at least one project
Milestones, last 90 days
2
newest Oct 2026

As of (newest check)

Our European pipeline tracker follows 4 data-centre projects of 1 MW or more that EcoDataCenter develops or co-develops, in 1 country; 2 are permitted or already being built. All of them are in Sweden.

50% are permitted or being built, against 44% across the whole tracker, so the pipeline is further along than the European average. The milestones we hold run from May 2025 to Oct 2026.

Projects by stage

  • In planning 2
  • Under construction 2

What the capacity figures measure

  • Facility, campus or unstated basis 1
  • First phase only 1
  • No capacity published 2

Too few published capacities for size bands.

Where EcoDataCenter is building

Latest milestones

The newest 2 steps we recorded, by market and stage.

  1. Oct 2026SwedenIn planning
  2. Aug 2026Sweden Land purchase agreement for 52 hectares signed with Smedjebacken MunicipalityIn planning
Method

Projects of 1 MW or more (or unstated), announced to under construction, that we have found and checked.

  • Projects EcoDataCenter develops or co-develops; a joint venture counts once per partner.
  • Capacities are on different bases: counted, never added.
  • From public filings and announcements; DC Blueprint is independent of EcoDataCenter. No project is listed.

Cite as: DC Blueprint, “EcoDataCenter data centre projects in Europe”, https://dcblueprint.com/sell/operators/ecodatacenter (checked 17 Oct 2026). © DC Blueprint.