Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Norway

Data centres in Norway

At a glance: Norway

Pipeline projects
19
6 permitted or being built
Checked 17 Oct 2026
New grid connections
Paused
midlertidig stopp i reservasjoner til fremtidig stort industriforbruk, in force since 22 Apr 2026. Nationwide, transmission
Checked 23 Oct 2026
Wholesale power price
45€/MWh
Day-ahead, 2025 mean, Norway
Calendar year 2025
Grid carbon intensity
28g CO₂/kWh
Yearly average, Norway
Latest full year
Latency to nearest major hub
12 ms
Round trip, Oslo to Amsterdam
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 19 data-centre projects in Norway, and 6 of them are permitted or being built.

Data centres in Norway in October 2026

The tracker follows 19 data centre projects of 1 MW or more in Norway, 6 of them permitted or being built. 15 developers are behind them, led by Nscale with 3 projects.

Projects by stage

  • Announced 13
  • Permitted 2
  • Under construction 4

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 4
  • Facility, campus or unstated basis 7
  • Grid connection 4
  • First phase only 2
  • No capacity published 2

Each capacity is on its own stated basis; never added.

Who is building in Norway

And 5 other developers with one project each. A joint venture counts once per partner. All operators and developers.

What changed

6 milestones in the last 90 days; the newest is from Sep 2026.

Power and grid in Norway

Paused

New grid connections are paused (nationwide, transmission, since 22 Apr 2026). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
28g CO₂/kWh
1st cleanest of 30 countries; 99% renewable or nuclear
Business electricity price, latest full year
57€/MWh
1st cheapest of 26; wholesale is 73% of it
Wholesale power, 2025 average
45€/MWh
3rd cheapest of 30
Cooling degree days
0a year
10-year national mean

Annual averages are national, for the latest full year.

Fibre latency from Oslo

Round trips from Oslo
ToRound trip, minimumPath lengthPath
Stockholm4.3 ms438 kmMapped fibre route
Copenhagen4.9 ms501 kmMapped fibre route
Helsinki7.7 ms787 kmStraight line (no mapped land route)
Amsterdam12 ms1,188 kmMapped fibre route
Frankfurt12 ms1,219 kmMapped fibre route
London15 ms1,528 kmMapped fibre route
Dublin15 ms1,566 kmMapped fibre route
Paris16 ms1,635 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

No dated rule on the calendar for Norway right now.

Formal refusals and bans since 2025

No area-wide rule recorded for Norway.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 3 official bodies, checked 11 October 2026: Elvia, Statnett, Våler kommune.