Step 4 · Sell
See what it sells for
Price, fill and contract terms, as scenarios.
Nscale data centre projects in Europe
- Projects tracked
- 5
- of 1 MW or more
- Permitted or being built
- 1
- 4 at announcement stage
- Countries
- 3
- with at least one project
- Milestones, last 90 days
- 1
- newest Sep 2026
Our European pipeline tracker follows 5 data-centre projects of 1 MW or more that Nscale develops or co-develops, in 3 countries; 1 is permitted or already being built. The largest share is in Norway, with 3 projects.
20% are permitted or being built, against 44% across the whole tracker, so the pipeline is earlier-stage than the European average. The milestones we hold run from Mar 2026 to Sep 2026.
Projects by stage
What the capacity figures measure
Stated size, where a figure is published
1 project has no published capacity and is not in a band. Bands mix bases, so read them as orders of size; never added.
Where Nscale is building
Latest milestones
The newest 3 steps we recorded, by market and stage.
- Sep 2026NorwayAnnounced
- Jun 2026Norway Nscale listed in Statnett's capacity queue with two power requests at Nedre Røssåga substation in HemnesAnnounced
- Apr 2026Finland Fortum signed a site securing and development agreement with NscaleAnnounced
Method
Projects of 1 MW or more (or unstated), announced to under construction, that we have found and checked.
- Projects Nscale develops or co-develops; a joint venture counts once per partner.
- Capacities are on different bases: counted, never added.
- From public filings and announcements; DC Blueprint is independent of Nscale. No project is listed.
Cite as: DC Blueprint, “Nscale data centre projects in Europe”, https://dcblueprint.com/sell/operators/nscale (checked 11 Oct 2026). © DC Blueprint.