Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Frankfurt

Data centres in Germany

At a glance: Germany

Pipeline projects
58
35 permitted or being built
Checked 18 Oct 2026
New grid connections
Rationed
Reifegradverfahren, in force since 1 Apr 2026. Nationwide, transmission
Checked 23 Oct 2026
Wholesale power price
90€/MWh
Day-ahead, 2025 mean, Germany
Calendar year 2025
Grid carbon intensity
330g CO₂/kWh
Yearly average, Germany
Latest full year
Next national rule date
1 Jan 2027
Germany’s EnEfG 100% renewable-electricity requirement takes effect
Applies in Germany
Latency to nearest major hub
3.8 ms
Round trip, Frankfurt to Amsterdam
Mapped fibre route, minimum

Data checked

On 18 October 2026 the pipeline tracker lists 58 data-centre projects in Germany, and 35 of them are permitted or being built.

Data centres in Germany in October 2026

The tracker follows 58 data centre projects of 1 MW or more in Germany, 35 of them permitted or being built. 38 developers are behind them, led by NTT Global Data Centers (5) and Microsoft (4).

Projects by stage

  • Announced 16
  • In planning 7
  • Permitted 9
  • Contractor appointed 2
  • Under construction 21
  • Structure complete 3

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 15
  • Facility, campus or unstated basis 17
  • Grid connection 10
  • First phase only 1
  • No capacity published 15

Each capacity is on its own stated basis; never added.

Who is building in Germany

And 28 other developers with up to 2 projects each. A joint venture counts once per partner. All operators and developers.

Where the data centres are in Germany

What changed

15 milestones in the last 90 days; the newest is from Oct 2026.

Power and grid in Germany

Rationed

New grid connections are rationed (nationwide, transmission, since 1 Apr 2026). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
330g CO₂/kWh
26th cleanest of 30 countries; 59% renewable or nuclear
Business electricity price, latest full year
216€/MWh
23rd cheapest of 26; wholesale is 46% of it
Wholesale power, 2025 average
90€/MWh
13th cheapest of 30

Climate at Frankfurt

Hours a year above 27 °C dry-bulb
282h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
51h
worst year 95 h
Hours a year above 20 °C wet-bulb
100h
limit for evaporative cooling

Hourly reanalysis at the city’s grid cell, 2016 to 2025.

Annual averages are national, for the latest full year.

Fibre latency from Frankfurt

Round trips from Frankfurt
ToRound trip, minimumPath lengthPath
Munich3.3 ms341 kmMapped fibre route
Zurich3.4 ms349 kmMapped fibre route
Brussels3.5 ms357 kmMapped fibre route
Amsterdam3.8 ms392 kmMapped fibre route
Paris5.9 ms599 kmMapped fibre route
London7.0 ms712 kmMapped fibre route
Dublin12 ms1,221 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force
GermanyApplies from 300 kW non-redundant nominal connected load; 100% renewable electricity from 1 Jan 2027In force
GermanySites running before 1 Jul 2026: PUE 1.5 or lower from 1 Jul 2027 and 1.3 from 1 Jul 2030In force
GermanySites starting operation from 1 Jul 2026: PUE 1.2 or lower and a reused-energy share of at least 10%, rising to 15% and 20% for sites starting from 1 Jul 2027 and 1 Jul 2028, within two years of start-upIn force
GermanyBill to relax the PUE limits to 1.6 and 1.4; committee hearing held 5 Oct 2026Proposed

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 1 Jan 2027Germany’s EnEfG 100% renewable-electricity requirement takes effect, unless Drucksache 21/8027 passes first and moves it to 1 January 2030
  3. 31 Mar 2027Germany’s register report due (every year)
  4. 15 May 2027EU database and French reports due (every year)
  5. 1 Jul 2027Germany’s EnEfG reused-energy share for new sites rises to 15% for data centres starting operation from this date
  6. 1 Jul 2027Germany’s EnEfG PUE ≤1.5 deadline for sites that started operating before 1 July 2026, unless Drucksache 21/8027 passes first

Formal refusals and bans since 2025

  1. 1 Jul 2026Eisenach, Thuringia Council granted a residents' petition; the draft zoning plan for a large data-centre site was withdrawn. Stopped for now; not a final rejection

1 decision on a single site since 2025, not listed here.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 22 official bodies, checked 23 October 2026: 50Hertz, Amprion, Bundesnetzagentur, City of Frankfurt am Main, Copernicus Climate Change Service (ERA5), EUR-Lex (Official Journal of the EU), German Federal Ministry for Digital Affairs, Hessian administrative courts, Hessian Ministry for Digital Affairs, MITNETZ STROM, Netztransparenz (German TSOs), NRM Netzdienste Rhein-Main, Regierungspräsidium Darmstadt, Stadt Butzbach, Stadt Eisenach, Stadt Hattersheim am Main, Stadt Hofheim am Taunus, Stadt Karben, Stadt Offenbach am Main, Stromnetz Berlin, TenneT, TransnetBW.