Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Dublin

Dublin data centre market

At a glance: Dublin

Pipeline projects
12
12 permitted or being built
Checked 17 Oct 2026
New grid connections
Paused
fully constrained, in force since 23 Nov 2021. Dublin, transmission
Checked 23 Oct 2026
Wholesale power price
114€/MWh
Day-ahead, 2025 mean, Ireland
Calendar year 2025
Grid carbon intensity
256g CO₂/kWh
Yearly average, Ireland
Latest full year
Next EU rule date
14 Dec 2026
The EU Commission’s minimum performance standards consultation and call for evidence closes
Applies EU-wide
Latency to nearest major hub
5.2 ms
Round trip, Dublin to London
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 12 data-centre projects around Dublin, and 12 of them are permitted or being built.

The Dublin data centre market in October 2026

The tracker follows 12 data centre projects of 1 MW or more around Dublin, 12 of them permitted or being built. 12 developers are behind them.

Projects by stage

  • Permitted 8
  • Under construction 3
  • Structure complete 1

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 2
  • Facility, campus or unstated basis 2
  • No capacity published 8

Each capacity is on its own stated basis; never added.

Who is building in Dublin

And 2 other developers with one project each. A joint venture counts once per partner. All operators and developers.

Where the data centres are around Dublin

  • South Dublin 8
  • Fingal 4

What changed

4 milestones in the last 90 days; the newest is from Sep 2026.

Power and grid for Dublin

Paused

New grid connections are paused (Dublin, transmission, since 23 Nov 2021). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
256g CO₂/kWh
19th cleanest of 30 countries; 48% renewable or nuclear
Business electricity price, latest full year
202€/MWh
21st cheapest of 26; wholesale is 73% of it
Wholesale power, 2025 average
114€/MWh
27th cheapest of 30

Climate at Dublin

Hours a year above 27 °C dry-bulb
0h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
0h
worst year 0 h
Hours a year above 20 °C wet-bulb
1h
limit for evaporative cooling

Hourly reanalysis at the city’s grid cell, 2016 to 2025.

Annual averages are national, for the latest full year.

Fibre latency from Dublin

Round trips from Dublin
ToRound trip, minimumPath lengthPath
London5.2 ms529 kmMapped fibre route
Amsterdam8.1 ms831 kmMapped fibre route
Brussels8.7 ms883 kmMapped fibre route
Paris9.1 ms929 kmMapped fibre route
Frankfurt12 ms1,221 kmMapped fibre route
Zurich14 ms1,426 kmMapped fibre route
Copenhagen14 ms1,471 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force
IrelandNew connecting data centres must match at least 80% of annual demand with additional renewable-electricity projectsIn force

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due (every year)
  3. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

  1. 12 Dec 2025Ireland, nationwide New large grid users must bring on-site or nearby dispatchable generation or storage and match demand with new Irish renewables. In force

2 decisions on single sites since 2025, not listed here.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 7 official bodies, checked 23 October 2026: An Coimisiún Pleanála, Central Statistics Office (Ireland), Copernicus Climate Change Service (ERA5), CRU (Irish regulator), EirGrid, EUR-Lex (Official Journal of the EU), South Dublin County Council.