Echelon Data Centres data centre projects in Europe
- Projects tracked
- 5
- of 1 MW or more
- Permitted or being built
- 2
- 1 at announcement stage
- Countries
- 3
- with at least one project
- Milestones, last 90 days
- 0
- newest Jun 2026
Our European pipeline tracker follows 5 data-centre projects of 1 MW or more that Echelon Data Centres develops or co-develops, in 3 countries; 2 are permitted or already being built. The largest share is in Ireland, with 3 projects.
40% are permitted or being built, against 44% across the whole tracker, so the pipeline is in line with the European average. The milestones we hold run from Sep 2025 to Jun 2026.
Projects by stage
What the capacity figures measure
Stated size, where a figure is published
2 projects have no published capacity and are not in a band. Bands mix bases, so read them as orders of size; never added.
Where Echelon Data Centres is building
Latest milestones
The newest 3 steps we recorded, by market and stage.
- Jun 2026DublinUnder construction
- Mar 2026Ireland Construction under wayUnder construction
- Nov 2025MadridAnnounced
Method
Projects of 1 MW or more (or unstated), announced to under construction, that we have found and checked.
- Projects Echelon Data Centres develops or co-develops; a joint venture counts once per partner.
- Capacities are on different bases: counted, never added.
- From public filings and announcements; DC Blueprint is independent of Echelon Data Centres. No project is listed.