Pure DC data centre projects in Europe

Projects tracked
6
of 1 MW or more
Permitted or being built
6
none at announcement stage
Countries
5
with at least one project
Milestones, last 90 days
4
newest Sep 2026

As of (newest check)

Our European pipeline tracker follows 6 data-centre projects of 1 MW or more that Pure DC develops or co-develops, in 5 countries; 6 are permitted or already being built. The largest share is in United Kingdom, with 2 projects.

100% are permitted or being built, against 44% across the whole tracker, so the pipeline is further along than the European average. The milestones we hold run from Nov 2025 to Sep 2026.

Projects by stage

  • Permitted 3
  • Under construction 3

What the capacity figures measure

  • IT load 2
  • Facility, campus or unstated basis 2
  • Grid connection 1
  • First phase only 1

Stated size, where a figure is published

  • 20 to 49 MW 1
  • 50 to 99 MW 4
  • 100 to 249 MW 1

Bands mix bases, so read them as orders of size; never added.

Where Pure DC is building

Latest milestones

The newest 3 steps we recorded, by market and stage.

  1. Sep 2026London Piling started on LON01B2, the campus's final build phaseUnder construction
  2. Jul 2026DublinPermitted
  3. Jul 2026LondonPermitted
Method

Projects of 1 MW or more (or unstated), announced to under construction, that we have found and checked.

  • Projects Pure DC develops or co-develops; a joint venture counts once per partner.
  • Capacities are on different bases: counted, never added.
  • From public filings and announcements; DC Blueprint is independent of Pure DC. No project is listed.