Step 4 · Sell

See what it sells for

Price, fill and contract terms, as scenarios.

Markets / Operators / NorthC

NorthC data centre projects in Europe

Projects tracked
4
of 1 MW or more
Permitted or being built
3
1 at announcement stage
Countries
3
with at least one project
Milestones, last 90 days
1
newest Sep 2026

As of (newest check)

Our European pipeline tracker follows 4 data-centre projects of 1 MW or more that NorthC develops or co-develops, in 3 countries; 3 are permitted or already being built. The largest share is in Germany, with 2 projects.

75% are permitted or being built, against 44% across the whole tracker, so the pipeline is further along than the European average. The milestones we hold run from Sep 2025 to Sep 2026.

Projects by stage

  • Announced 1
  • Contractor appointed 1
  • Under construction 2

What the capacity figures measure

  • IT load 1
  • Facility, campus or unstated basis 3

Stated size, where a figure is published

  • Under 20 MW 4

Bands mix bases, so read them as orders of size; never added.

Where NorthC is building

Latest milestones

The newest 2 steps we recorded, by market and stage.

  1. Sep 2026Frankfurt Preparatory construction works startedUnder construction
  2. Apr 2026Amsterdam Phase 2 started: the first floor of the existing data centre is fitted out.Under construction
Method

Projects of 1 MW or more (or unstated), announced to under construction, that we have found and checked.

  • Projects NorthC develops or co-develops; a joint venture counts once per partner.
  • Capacities are on different bases: counted, never added.
  • From public filings and announcements; DC Blueprint is independent of NorthC. No project is listed.

Cite as: DC Blueprint, “NorthC data centre projects in Europe”, https://dcblueprint.com/sell/operators/northc (checked 18 Oct 2026). © DC Blueprint.