NorthC data centre projects in Europe
- Projects tracked
- 4
- of 1 MW or more
- Permitted or being built
- 3
- 1 at announcement stage
- Countries
- 3
- with at least one project
- Milestones, last 90 days
- 1
- newest Sep 2026
Our European pipeline tracker follows 4 data-centre projects of 1 MW or more that NorthC develops or co-develops, in 3 countries; 3 are permitted or already being built. The largest share is in Germany, with 2 projects.
75% are permitted or being built, against 44% across the whole tracker, so the pipeline is further along than the European average. The milestones we hold run from Sep 2025 to Sep 2026.
Projects by stage
What the capacity figures measure
Stated size, where a figure is published
Bands mix bases, so read them as orders of size; never added.
Where NorthC is building
Latest milestones
The newest 2 steps we recorded, by market and stage.
- Sep 2026Frankfurt Preparatory construction works startedUnder construction
- Apr 2026Amsterdam Phase 2 started: the first floor of the existing data centre is fitted out.Under construction
Method
Projects of 1 MW or more (or unstated), announced to under construction, that we have found and checked.
- Projects NorthC develops or co-develops; a joint venture counts once per partner.
- Capacities are on different bases: counted, never added.
- From public filings and announcements; DC Blueprint is independent of NorthC. No project is listed.