Step 1 · Plan

Build your multi-year plan

Site, grid, costs, revenue and returns in one case.

Project Data centre, Frankfurt Frankfurt, 20 MW, 2 phases

Example values. Change any of them and they become your project, kept in this browser. Create a free account to keep it

Market and customers

5 of 7
Customer base
  • 20% Retail
  • 30% Wholesale
  • 50% Big customers

Retail enterpriseCabinets, short terms

%
€/kW-mo
%

WholesaleSuites and cages

%
€/kW-mo

Big customersHyperscale and neocloud halls, long terms

Share

50%, the rest

€/kW-mo
%
MW
%
Customers’ electricity
Contracts and interconnection
%
%/yr
€/kW
%
€/mo
kW
Monthly recurring revenue Premium 786 retail cabinets
Contracted, stabilised 17.7 MW 88% of built
Average price Premium Per kW a month, blended
Full by 2033 Contracted to the stabilised level

Revenue by customer, stabilised

Revenue by customer, stabilised
CustomerContractedPriceShare of rentChurn a yearFills in
Retail enterprise3.5 MWPremiumPremium8.0%50 months
Wholesale suites5.3 MWPremiumPremium3.0%25 months
Big customers8.8 MWPremiumPremium0.0%12 months
All customers17.7 MWPremium100%2.5%

Retail oversubscription 20%: customers draw 62% of built capacity at the average load.

Market: Frankfurt

Market: Frankfurt
IndicatorValue
Pipeline projects on the map35
Grid wait for a new connection9.0 years
Planning and permits7 months

Reference data for the site and the grid

Live and monthly grid data, the power plant map, siting costs, market comparison and fibre latency, each with its sources and dates.

Grid and power

Siting and markets