Step 1 · Plan

Build your multi-year plan

Site, grid, costs, revenue and returns in one case.

Project Data centre, Frankfurt Frankfurt, 20 MW, 2 phases

Example values. Change any of them and they become your project, kept in this browser. Create a free account to keep it

Construction

3 of 7
€M
Grid capacity
years
%
Cost and programme in detail
€M/MW
%
%/yr
%
€M
€M
MVA
€k/MW
€M
months
months
months
months
Long-lead equipment ordered

Cost plan, today’s prices

Cost plan, today’s prices
ElementCostPer MW of ITShare (survey range)
Electricalswitchgear, UPS, generators, distributionPremiumPremium50% (48–54%)
Mechanicalcooling units, heat rejection, pumps and pipeworkPremiumPremium24% (22–33%)
Buildingcore and shellPremiumPremium14% (9–14%)
Fire detection and suppressiondetection and gas suppression in the IT halls, electrical and plant roomsPremiumPremium1%
White-space fit-outcontainment, ceilings, lighting; power and cooling distribution sit abovePremiumPremium2%
Security and controlsaccess control, CCTV, building and power managementPremiumPremium2%
Contractor managementpreliminaries and project managementPremiumPremium8% (about 10%)
ConstructionPremiumPremium100%
of which shell and site plant, built with phase 1Premium32%
of which hall fit-out, as each phase is builtPremiumPremium68%
Fees and permits, 6%PremiumPremium
Planning allowance, 10%PremiumPremium
LandPremiumPremium
Grid connection and site worksPremiumPremium
Development costPremiumPremium

Construction for Frankfurt at Premium per MW for a reference design (N+1 power and cooling, 2N distribution, air-cooled chillers with free cooling, 8 kW racks), shaped by component for this design: × 1.00. Shares in brackets: typical European ranges. Excludes customers’ IT and cabinets unless the operator supplies them. Accuracy: AACE Class 5, an order-of-magnitude estimate (typically −20% to −50% and +30% to +100%).

  • Pre-application: Oct 2026 to Apr 2027
  • Planning and permits: Apr 2027 to Nov 2027
  • Long-lead equipment: Nov 2027 to Aug 2029, sets the date
  • Construction, phase 1: Jun 2028 to Feb 2030
  • Commissioning and handover: Feb 2030 to May 2030, sets the date
  • Phase 2, 10.0 MW: Jun 2031 to May 2033
First hall ready May 2030: long-lead equipment sets the date (red). Reserving transformers and generators before permits (Construction step) moves the date.

Reference data for the site and the grid

Live and monthly grid data, the power plant map, siting costs, market comparison and fibre latency, each with its sources and dates.

Grid and power

Siting and markets