Step 1 · Plan
Build your multi-year plan
Site, grid, costs, revenue and returns in one case.
Cost plan, today’s prices
| Element | Cost | Per MW of IT | Share (survey range) |
|---|---|---|---|
| Electricalswitchgear, UPS, generators, distribution | Premium | Premium | 50% (48–54%) |
| Mechanicalcooling units, heat rejection, pumps and pipework | Premium | Premium | 24% (22–33%) |
| Buildingcore and shell | Premium | Premium | 14% (9–14%) |
| Fire detection and suppressiondetection and gas suppression in the IT halls, electrical and plant rooms | Premium | Premium | 1% |
| White-space fit-outcontainment, ceilings, lighting; power and cooling distribution sit above | Premium | Premium | 2% |
| Security and controlsaccess control, CCTV, building and power management | Premium | Premium | 2% |
| Contractor managementpreliminaries and project management | Premium | Premium | 8% (about 10%) |
| Construction | Premium | Premium | 100% |
| of which shell and site plant, built with phase 1 | Premium | 32% | |
| of which hall fit-out, as each phase is built | Premium | Premium | 68% |
| Fees and permits, 6% | Premium | Premium | |
| Planning allowance, 10% | Premium | Premium | |
| Land | Premium | Premium | |
| Grid connection and site works | Premium | Premium | |
| Development cost | Premium | Premium |
Construction for Frankfurt at Premium per MW for a reference design (N+1 power and cooling, 2N distribution, air-cooled chillers with free cooling, 8 kW racks), shaped by component for this design: × 1.00. Shares in brackets: typical European ranges. Excludes customers’ IT and cabinets unless the operator supplies them. Accuracy: AACE Class 5, an order-of-magnitude estimate (typically −20% to −50% and +30% to +100%).
- Pre-application: Oct 2026 to Apr 2027
- Planning and permits: Apr 2027 to Nov 2027
- Long-lead equipment: Nov 2027 to Aug 2029, sets the date
- Construction, phase 1: Jun 2028 to Feb 2030
- Commissioning and handover: Feb 2030 to May 2030, sets the date
- Phase 2, 10.0 MW: Jun 2031 to May 2033
Reference data for the site and the grid
Live and monthly grid data, the power plant map, siting costs, market comparison and fibre latency, each with its sources and dates.
Grid and power
- Live gridCarbon intensity, day-ahead price and renewable share for the European markets, refreshed through the day.
- Grid indexThe monthly index of European grid conditions for data centres, with its method and dated sources.
- Grid signalA grid signal for compute schedulers: a waiting list, with a dated sample of the data.
- Power plant mapEvery power plant of 50 MW or more by fuel and capacity, with the countries around it.
Siting and markets
- Site finderScore any point in Europe on grid connections, the nearest substation, generation, fibre and the electricity bill.
- Market comparisonThe main data-centre markets side by side: power, cooling hours and flexibility value.
- Fibre latencyRound-trip fibre latency between European data-centre cities, with the route behind each figure.