Step 4 · Sell

See what it sells for

Price, fill and contract terms, as scenarios.

Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in London

Data centres in the United Kingdom

At a glance: United Kingdom

Pipeline projects
73
36 permitted or being built
Checked 17 Oct 2026
New grid connections
Paused
paused to new connection applications, in force since 30 Jun 2025. Nationwide, transmission
Checked 23 Oct 2026
Wholesale power price
94€/MWh
Day-ahead, 2025 mean, United Kingdom
Calendar year 2025
Grid carbon intensity
217g CO₂/kWh
Yearly average, United Kingdom
Latest full year
Next national rule date
26 Oct 2026
House of Lords report stage of the United Kingdom’s Cyber Security and Resilience Bill
Applies in the United Kingdom
Latency to nearest major hub
4.0 ms
Round trip, London to Paris
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 73 data-centre projects in the United Kingdom, and 36 of them are permitted or being built.

Data centres in the United Kingdom in October 2026

The tracker follows 73 data centre projects of 1 MW or more in the United Kingdom, 36 of them permitted or being built. 56 developers are behind them, led by Apatura (5), ILI Group (3) and Microsoft (3).

Projects by stage

  • Announced 8
  • In planning 29
  • Permitted 29
  • Contractor appointed 1
  • Under construction 6

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 12
  • Facility, campus or unstated basis 35
  • Grid connection 2
  • No capacity published 24

Each capacity is on its own stated basis; never added.

Who is building in the United Kingdom

And 46 other developers with up to 2 projects each; 2 projects with no developer named. A joint venture counts once per partner. All operators and developers.

Where the data centres are in the United Kingdom

  • London 37
  • Elsewhere in the United Kingdom 36

What changed

27 milestones in the last 90 days; the newest is from Oct 2026.

Power and grid in the United Kingdom

Paused

New grid connections are paused (nationwide, transmission, since 30 Jun 2025). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
217g CO₂/kWh
17th cleanest of 30 countries; 64% renewable or nuclear
Wholesale power, 2025 average
94€/MWh
14th cheapest of 30

Climate at London

Hours a year above 27 °C dry-bulb
61h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
4h
worst year 17 h
Hours a year above 20 °C wet-bulb
45h
limit for evaporative cooling

Hourly reanalysis at the city’s grid cell, 2016 to 2025.

Annual averages are national, for the latest full year.

Fibre latency from London

Round trips from London
ToRound trip, minimumPath lengthPath
Brussels3.5 ms357 kmMapped fibre route
Paris4.0 ms409 kmMapped fibre route
Amsterdam4.0 ms411 kmMapped fibre route
Dublin5.2 ms529 kmMapped fibre route
Frankfurt7.0 ms712 kmMapped fibre route
Zurich8.8 ms900 kmMapped fibre route
Munich10.0 ms1,017 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Next dates

  1. 26 Oct 2026House of Lords report stage of the United Kingdom’s Cyber Security and Resilience Bill, which would regulate data centres from 1 MW rated IT load
  2. 1 Jan 2027the United Kingdom’s amended Climate Change Agreements regulations come into force and cover data facilities with an electricity supply of at least 200 kW

Formal refusals and bans since 2025

No area-wide rule recorded for the United Kingdom.

2 decisions on single sites since 2025, not listed here.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 14 official bodies, checked 23 October 2026: Copernicus Climate Change Service (ERA5), Department for Energy Security and Net Zero, Fife Council, GOV.UK, London Assembly Planning and Regeneration Committee, London Borough of Havering, NESO, Ofgem, Old Oak and Park Royal Development Corporation, Planning Inspectorate, Redcar and Cleveland Borough Council, Scottish Government planning appeals (DPEA), Slough Borough Council, Thurrock Council.