Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Amsterdam

Data centres in the Netherlands

At a glance: Netherlands

Pipeline projects
24
14 permitted or being built
Checked 18 Oct 2026
New grid connections
Rationed
maximaal aansluitvermogen datacentrum, in force since 8 Apr 2026. Amsterdam, distribution
Checked 23 Oct 2026
Wholesale power price
88€/MWh
Day-ahead, 2025 mean, Netherlands
Calendar year 2025
Grid carbon intensity
254g CO₂/kWh
Yearly average, Netherlands
Latest full year
Next EU rule date
14 Dec 2026
The EU Commission’s minimum performance standards consultation and call for evidence closes
Applies EU-wide
Latency to nearest major hub
3.8 ms
Round trip, Amsterdam to Frankfurt
Mapped fibre route, minimum

Data checked

On 18 October 2026 the pipeline tracker lists 24 data-centre projects in the Netherlands, and 14 of them are permitted or being built.

Data centres in the Netherlands in October 2026

The tracker follows 24 data centre projects of 1 MW or more in the Netherlands, 14 of them permitted or being built. 17 developers are behind them, led by EdgeConneX (6), Digital Realty (2) and Equinix (2).

Projects by stage

  • Announced 2
  • In planning 8
  • Permitted 8
  • Under construction 6

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 3
  • Facility, campus or unstated basis 9
  • Grid connection 3
  • First phase only 3
  • No capacity published 6

Each capacity is on its own stated basis; never added.

Who is building in the Netherlands

And 7 other developers with one project each. A joint venture counts once per partner. All operators and developers.

Where the data centres are in the Netherlands

What changed

9 milestones in the last 90 days; the newest is from Oct 2026.

Power and grid in the Netherlands

Rationed

New grid connections are rationed (Amsterdam, distribution, since 8 Apr 2026). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
254g CO₂/kWh
18th cleanest of 30 countries; 54% renewable or nuclear
Business electricity price, latest full year
165€/MWh
16th cheapest of 26; wholesale is 61% of it
Wholesale power, 2025 average
88€/MWh
12th cheapest of 30

Climate at Amsterdam

Hours a year above 27 °C dry-bulb
80h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
8h
worst year 24 h
Hours a year above 20 °C wet-bulb
94h
limit for evaporative cooling

Hourly reanalysis at the city’s grid cell, 2016 to 2025.

Annual averages are national, for the latest full year.

Fibre latency from Amsterdam

Round trips from Amsterdam
ToRound trip, minimumPath lengthPath
Brussels1.8 ms181 kmMapped fibre route
Frankfurt3.8 ms392 kmMapped fibre route
London4.0 ms411 kmMapped fibre route
Paris4.4 ms453 kmMapped fibre route
Berlin6.4 ms651 kmMapped fibre route
Zurich7.0 ms715 kmMapped fibre route
Dublin8.1 ms831 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force
NetherlandsNew hyperscale data centres restricted nationally to two designated areasIn force

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due (every year)
  3. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

  1. 23 Sep 2026Westland, South Holland Council adopted a ban on new data centres across nearly all of the municipality. Adopted; not yet in force (appeal period to 20 Nov 2026)
  2. 23 Jun 2026Oldambt, Groningen Temporary ban on new data centres on business land while the zoning plan is revised. In force
  3. 26 May 2026Heusden, North Brabant Temporary ban on new data centres, up to 18 months, while the zoning plan is revised. In force
  4. 12 May 2026Zaanstad, near Amsterdam Zoning plan bars new data centres above 2,000 m² floor area and 5 MVA. In force
  5. 11 Jun 2025Amsterdam Zoning plan bars new or larger data centres above 2,000 m² floor area and 5 MVA. In force

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 18 official bodies, checked 23 October 2026: ACM (Dutch regulator), Commissie voor de milieueffectrapportage, Copernicus Climate Change Service (ERA5), EUR-Lex (Official Journal of the EU), Gemeente Aalsmeer, Gemeente Amsterdam, Gemeente Diemen, Gemeente Haarlemmermeer, Gemeente Lelystad, Hoogheemraadschap van Rijnland, Liander, Netbeheer Nederland, Officiële bekendmakingen (Dutch official gazette), Omgevingsdienst Noordzeekanaalgebied, Provincie Flevoland, Provincie Groningen, Provincie Noord-Holland, TenneT.