Step 4 · Sell

See what it sells for

Price, fill and contract terms, as scenarios.

Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Portugal

Data centres in Portugal

At a glance: Portugal

Pipeline projects
7
4 permitted or being built
Checked 17 Oct 2026
New grid connections
Rationed
zona de grande procura, in force since 2 Feb 2026. Nationwide, transmission
Checked 23 Oct 2026
Wholesale power price
68€/MWh
Day-ahead, 2025 mean, Portugal
Calendar year 2025
Grid carbon intensity
128g CO₂/kWh
Yearly average, Portugal
Latest full year
Next EU rule date
14 Dec 2026
The EU Commission’s minimum performance standards consultation and call for evidence closes
Applies EU-wide
Latency to nearest major hub
16 ms
Round trip, Lisbon to Paris
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 7 data-centre projects in Portugal, and 4 of them are permitted or being built.

Data centres in Portugal in October 2026

The tracker follows 7 data centre projects of 1 MW or more in Portugal, 4 of them permitted or being built. 5 developers are behind them, led by Merlin Properties and Start Campus with 2 projects each.

Projects by stage

  • Announced 3
  • Permitted 1
  • Under construction 3

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 2
  • Facility, campus or unstated basis 4
  • First phase only 1

Each capacity is on its own stated basis; never added.

Who is building in Portugal

A joint venture counts once per partner. All operators and developers.

What changed

3 milestones in the last 90 days; the newest is from Aug 2026.

Power and grid in Portugal

Rationed

New grid connections are rationed (nationwide, transmission, since 2 Feb 2026). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
128g CO₂/kWh
10th cleanest of 30 countries; 81% renewable or nuclear
Business electricity price, latest full year
128€/MWh
9th cheapest of 26; wholesale is 61% of it
Wholesale power, 2025 average
68€/MWh
6th cheapest of 30
Cooling degree days
224a year
10-year national mean

Annual averages are national, for the latest full year.

Fibre latency from Lisbon

Round trips from Lisbon
ToRound trip, minimumPath lengthPath
Madrid5.2 ms536 kmMapped fibre route
Marseille16 ms1,585 kmMapped fibre route
Paris16 ms1,606 kmMapped fibre route
Dublin16 ms1,643 kmStraight line (no mapped land route)
London20 ms1,998 kmMapped fibre route
Milan20 ms2,013 kmMapped fibre route
Amsterdam20 ms2,056 kmMapped fibre route
Frankfurt21 ms2,168 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due (every year)
  3. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Portugal.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 4 official bodies, checked 23 October 2026: DGEG (Portuguese energy directorate), EUR-Lex (Official Journal of the EU), Government of Portugal, REN.