Step 4 · Sell
See what it sells for
Price, fill and contract terms, as scenarios.
Markets and operators: who is building where
The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.
Data centres in Denmark
At a glance: Denmark
- Pipeline projects
- 9
- 2 permitted or being built
- Checked 11 Oct 2026
- New grid connections
- Rationed
- kapacitetstildeling. Nationwide, transmission
- Checked 23 Oct 2026
- Wholesale power price
- 83€/MWh
- Day-ahead, 2025 mean, Denmark
- Calendar year 2025
- Grid carbon intensity
- 100g CO₂/kWh
- Yearly average, Denmark
- Latest full year
- Next EU rule date
- 14 Dec 2026
- The EU Commission’s minimum performance standards consultation and call for evidence closes
- Applies EU-wide
- Latency to nearest major hub
- 6.8 ms
- Round trip, Copenhagen to Amsterdam
- Mapped fibre route, minimum
On 11 October 2026 the pipeline tracker lists 9 data-centre projects in Denmark, and 2 of them are permitted or being built.
Data centres in Denmark in October 2026
The tracker follows 9 data centre projects of 1 MW or more in Denmark, 2 of them permitted or being built. 10 developers are behind them.
Projects by stage
What the capacity figures measure
Each capacity is on its own stated basis; never added.
Who is building in Denmark
A joint venture counts once per partner. All operators and developers.
What changed
6 milestones in the last 90 days; the newest is from Oct 2026.
Power and grid in Denmark
Rationed
New grid connections are rationed (nationwide, transmission). Checked 23 Oct 2026. Every country’s grid connections.
Over a year, country level
- Grid carbon, latest full-year average
- 100g CO₂/kWh
- 7th cleanest of 30 countries; 94% renewable or nuclear
- Business electricity price, latest full year
- 176€/MWh
- 18th cheapest of 26; wholesale is 53% of it
- Wholesale power, 2025 average
- 83€/MWh
- 8th cheapest of 30
Climate at Copenhagen
- Hours a year above 27 °C dry-bulb
- 30h
- mean of 2016 to 2025
- Hours a year above 32 °C dry-bulb
- 0h
- worst year 0 h
- Hours a year above 20 °C wet-bulb
- 40h
- limit for evaporative cooling
Hourly reanalysis at the city’s grid cell, 2016 to 2025.
Annual averages are national, for the latest full year.
Fibre latency from Copenhagen
| To | Round trip, minimum | Path length | Path |
|---|---|---|---|
| Berlin | 3.9 ms | 396 km | Mapped fibre route |
| Oslo | 4.9 ms | 501 km | Mapped fibre route |
| Stockholm | 5.6 ms | 573 km | Mapped fibre route |
| Amsterdam | 6.8 ms | 690 km | Mapped fibre route |
| Frankfurt | 7.1 ms | 721 km | Mapped fibre route |
| London | 11 ms | 1,099 km | Mapped fibre route |
| Paris | 11 ms | 1,137 km | Mapped fibre route |
| Dublin | 14 ms | 1,471 km | Mapped fibre route |
Floors for light in fibre, city centre to city centre; operator fibre adds to this.
Rules and dates
| Where | Rule | Status |
|---|---|---|
| EU | Reporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027 | In force |
| EU | Waste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasible | In force |
| EU | Common rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 Oct | Adopted, not in force |
Next dates
- 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
- 15 May 2027EU database and French reports due (every year)
- 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption
Formal refusals and bans since 2025
- Oct 2026Denmark, nationwide Law places data centres last in the grid connection queue unless they serve a critical public function. In force from 12 Oct 2026
- 2 Mar 2026Denmark, transmission grid Grid operator paused new connection agreements. No resumption confirmed
Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.
Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 8 official bodies, checked 23 October 2026: Copernicus Climate Change Service (ERA5), Danish Ministry of Climate, Energy and Utilities, Energinet, EUR-Lex (Official Journal of the EU), Radius Elnet, Retsinformation (Danish law), Ringkøbing-Skjern Kommune, Varde Kommune.