Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Madrid

Data centres in Spain

At a glance: Spain

Pipeline projects
51
23 permitted or being built
Checked 19 Oct 2026
New grid connections
Rationed
concurso de acceso de demanda, in force since 17 Jul 2025. Nationwide, transmission
Checked 23 Oct 2026
Wholesale power price
67€/MWh
Day-ahead, 2025 mean, Spain
Calendar year 2025
Grid carbon intensity
154g CO₂/kWh
Yearly average, Spain
Latest full year
Next EU rule date
14 Dec 2026
The EU Commission’s minimum performance standards consultation and call for evidence closes
Applies EU-wide
Latency to nearest major hub
11 ms
Round trip, Madrid to Paris
Mapped fibre route, minimum

Data checked

On 19 October 2026 the pipeline tracker lists 51 data-centre projects in Spain, and 23 of them are permitted or being built.

Data centres in Spain in October 2026

The tracker follows 51 data centre projects of 1 MW or more in Spain, 23 of them permitted or being built. 38 developers are behind them, led by Merlin Properties (7), Amazon Web Services (3) and EdgeMode (3).

Projects by stage

  • Announced 20
  • In planning 8
  • Permitted 5
  • Under construction 17
  • Structure complete 1

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 9
  • Facility, campus or unstated basis 18
  • First phase only 5
  • No capacity published 19

Each capacity is on its own stated basis; never added.

Who is building in Spain

And 28 other developers with one project each. A joint venture counts once per partner. All operators and developers.

Where the data centres are in Spain

  • Elsewhere in Spain 30
  • Madrid 21

What changed

23 milestones in the last 90 days; the newest is from Oct 2026.

Power and grid in Spain

Rationed

New grid connections are rationed (nationwide, transmission, since 17 Jul 2025). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
154g CO₂/kWh
13th cleanest of 30 countries; 75% renewable or nuclear
Business electricity price, latest full year
126€/MWh
8th cheapest of 26; wholesale is 71% of it
Wholesale power, 2025 average
67€/MWh
5th cheapest of 30

Climate at Madrid

Hours a year above 27 °C dry-bulb
1,117h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
441h
worst year 508 h
Hours a year above 20 °C wet-bulb
63h
limit for evaporative cooling

Hourly reanalysis at the city’s grid cell, 2016 to 2025.

Annual averages are national, for the latest full year.

Fibre latency from Madrid

Round trips from Madrid
ToRound trip, minimumPath lengthPath
Lisbon5.2 ms536 kmMapped fibre route
Marseille10 ms1,052 kmMapped fibre route
Paris11 ms1,149 kmMapped fibre route
Milan15 ms1,480 kmMapped fibre route
London15 ms1,542 kmMapped fibre route
Amsterdam16 ms1,600 kmMapped fibre route
Frankfurt17 ms1,712 kmMapped fibre route
Dublin20 ms2,057 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force
SpainDraft Royal Decree: grid permits from 1 MW of access power tied to PUE 1.15 or lower and 80% renewable supply matched hour by hour; hearing closed 10 Sep 2026, no approval dateProposed

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due (every year)
  3. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Spain.

11 decisions on single sites since 2025, not listed here.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 5 official bodies, checked 23 October 2026: BOE (Spanish official gazette), Copernicus Climate Change Service (ERA5), EUR-Lex (Official Journal of the EU), MITECO, Red Eléctrica.