Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Poland

Data centres in Poland

At a glance: Poland

Pipeline projects
12
2 permitted or being built
Checked 17 Oct 2026
New grid connections
Congested
dostępne moce przyłączeniowe odbiorcze, in force since 30 Sep 2026. Nationwide, transmission
Checked 23 Oct 2026
Wholesale power price
104€/MWh
Day-ahead, 2025 mean, Poland
Calendar year 2025
Grid carbon intensity
591g CO₂/kWh
Yearly average, Poland
Latest full year
Next EU rule date
14 Dec 2026
The EU Commission’s minimum performance standards consultation and call for evidence closes
Applies EU-wide
Latency to nearest major hub
9.5 ms
Round trip, Warsaw to Frankfurt
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 12 data-centre projects in Poland, and 2 of them are permitted or being built.

Data centres in Poland in October 2026

The tracker follows 12 data centre projects of 1 MW or more in Poland, 2 of them permitted or being built. 12 developers are behind them.

Projects by stage

  • Announced 9
  • In planning 1
  • Permitted 2

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 1
  • Facility, campus or unstated basis 8
  • Grid connection 1
  • No capacity published 2

Each capacity is on its own stated basis; never added.

Who is building in Poland

  • Atman 1
  • Beyond.pl 1
  • Centralna Grupa Energetyczna 1
  • Data4 1
  • DL Invest Group 1
  • Greykite European Real Estate Fund I 1
  • Hillwood Polska 1
  • Polcom 1
  • Twenty20 Energy Poland 1
  • WBS Power 1

And 2 other developers with one project each; 1 project with no developer named. A joint venture counts once per partner. All operators and developers.

What changed

4 milestones in the last 90 days; the newest is from Sep 2026.

Power and grid in Poland

Congested

New grid connections are congested (nationwide, transmission, since 30 Sep 2026). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
591g CO₂/kWh
29th cleanest of 30 countries; 31% renewable or nuclear
Business electricity price, latest full year
233€/MWh
25th cheapest of 26; wholesale is 29% of it
Wholesale power, 2025 average
104€/MWh
19th cheapest of 30

Climate at Warsaw

Hours a year above 27 °C dry-bulb
215h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
14h
worst year 27 h
Hours a year above 20 °C wet-bulb
186h
limit for evaporative cooling

Hourly reanalysis at the city’s grid cell, 2016 to 2025.

Annual averages are national, for the latest full year.

Fibre latency from Warsaw

Round trips from Warsaw
ToRound trip, minimumPath lengthPath
Berlin5.6 ms568 kmMapped fibre route
Vienna6.4 ms654 kmMapped fibre route
Prague6.7 ms685 kmMapped fibre route
Frankfurt9.5 ms965 kmMapped fibre route
Amsterdam12 ms1,217 kmMapped fibre route
Paris15 ms1,536 kmMapped fibre route
London16 ms1,624 kmMapped fibre route
Dublin20 ms2,046 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due (every year)
  3. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

  1. 26 Aug 2026Dobre, Masovia Council removed a data-centre zone from the draft general plan. Standing

1 decision on a single site since 2025, not listed here.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 5 official bodies, checked 23 October 2026: City of Gliwice, Copernicus Climate Change Service (ERA5), Dziennik Ustaw (Polish official journal), EUR-Lex (Official Journal of the EU), PSE.