Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Milan

Data centres in Italy

At a glance: Italy

Pipeline projects
52
12 permitted or being built
Checked 17 Oct 2026
New grid connections
No pause or cap
No rule in force for Italy pauses, rations or conditions them
Checked 23 Oct 2026
Wholesale power price
122€/MWh
Day-ahead, 2025 mean, Italy
Calendar year 2025
Grid carbon intensity
285g CO₂/kWh
Yearly average, Italy
Latest full year
Next EU rule date
14 Dec 2026
The EU Commission’s minimum performance standards consultation and call for evidence closes
Applies EU-wide
Latency to nearest major hub
5.6 ms
Round trip, Milan to Frankfurt
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 52 data-centre projects in Italy, and 12 of them are permitted or being built.

Data centres in Italy in October 2026

The tracker follows 52 data centre projects of 1 MW or more in Italy, 12 of them permitted or being built. 44 developers are behind them; none has more than 2 projects.

Projects by stage

  • Announced 19
  • In planning 21
  • Permitted 6
  • Under construction 6

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 10
  • Facility, campus or unstated basis 24
  • Grid connection 3
  • No capacity published 15

Each capacity is on its own stated basis; never added.

Who is building in Italy

And 34 other developers with one project each; 2 projects with no developer named. A joint venture counts once per partner. All operators and developers.

Where the data centres are in Italy

  • Milan 30
  • Elsewhere in Italy 22

What changed

23 milestones in the last 90 days; the newest is from Oct 2026.

Power and grid in Italy

No pause or cap

No rule in force pauses, rations or conditions new grid connections here. Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
285g CO₂/kWh
23rd cleanest of 30 countries; 49% renewable or nuclear
Business electricity price, latest full year
172€/MWh
17th cheapest of 26; wholesale is 69% of it
Wholesale power, 2025 average
122€/MWh
29th cheapest of 30

Climate at Milan

Hours a year above 27 °C dry-bulb
789h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
146h
worst year 285 h
Hours a year above 20 °C wet-bulb
1,136h
limit for evaporative cooling

Hourly reanalysis at the city’s grid cell, 2016 to 2025.

Annual averages are national, for the latest full year.

Fibre latency from Milan

Round trips from Milan
ToRound trip, minimumPath lengthPath
Zurich2.2 ms225 kmMapped fibre route
Munich4.1 ms418 kmMapped fibre route
Marseille4.3 ms440 kmMapped fibre route
Frankfurt5.6 ms573 kmMapped fibre route
Paris8.0 ms817 kmMapped fibre route
Amsterdam9.2 ms939 kmMapped fibre route
London11 ms1,115 kmMapped fibre route
Dublin16 ms1,642 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force
ItalySingle authorisation for building, expanding and running a data centre and its grid connection, decided within 10 months (up to 3 more in exceptional cases); no power thresholdIn force

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due (every year)
  3. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Italy.

2 decisions on single sites since 2025, not listed here.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 9 official bodies, checked 23 October 2026: Camera dei deputati, Comune di Bollate, Comune di Treviglio, Comune di Zibido San Giacomo, Copernicus Climate Change Service (ERA5), EUR-Lex (Official Journal of the EU), Italian Ministry of the Environment and Energy Security, Regione Lombardia, Terna.