Markets and operators: who is building where
The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.
Data centres in Czechia
At a glance: Czechia
- Pipeline projects
- 5
- 2 permitted or being built
- Checked 17 Oct 2026
- New grid connections
- Conditional
- červená / oranžová / zelená, in force since 1 Sep 2026. Nationwide, transmission
- Checked 23 Oct 2026
- Wholesale power price
- 97€/MWh
- Day-ahead, 2025 mean, Czechia
- Calendar year 2025
- Grid carbon intensity
- 402g CO₂/kWh
- Yearly average, Czechia
- Latest full year
- Next national rule date
- 31 Dec 2026
- Deadline for existing data centres above 1 MW in Czechia to meet the waste-heat duty
- Applies in Czechia
- Latency to nearest major hub
- 4.4 ms
- Round trip, Prague to Frankfurt
- Mapped fibre route, minimum
On 17 October 2026 the pipeline tracker lists 5 data-centre projects in Czechia, and 2 of them are permitted or being built.
Data centres in Czechia in October 2026
The tracker follows 5 data centre projects of 1 MW or more in Czechia, 2 of them permitted or being built. 5 developers are behind them.
Projects by stage
What the capacity figures measure
Each capacity is on its own stated basis; never added.
Who is building in Czechia
A joint venture counts once per partner. All operators and developers.
What changed
2 milestones in the last 90 days; the newest is from Oct 2026.
Power and grid in Czechia
Conditional
New grid connections are conditional (nationwide, transmission, since 1 Sep 2026). Checked 23 Oct 2026. Every country’s grid connections.
Over a year, country level
- Grid carbon, latest full-year average
- 402g CO₂/kWh
- 27th cleanest of 30 countries; 59% renewable or nuclear
- Business electricity price, latest full year
- 233€/MWh
- 26th cheapest of 26; wholesale is 47% of it
- Wholesale power, 2025 average
- 97€/MWh
- 15th cheapest of 30
- Cooling degree days
- 33a year
- 10-year national mean
Annual averages are national, for the latest full year.
Fibre latency from Prague
| To | Round trip, minimum | Path length | Path |
|---|---|---|---|
| Vienna | 2.8 ms | 286 km | Mapped fibre route |
| Berlin | 3.1 ms | 320 km | Mapped fibre route |
| Munich | 3.5 ms | 355 km | Mapped fibre route |
| Frankfurt | 4.4 ms | 445 km | Mapped fibre route |
| Amsterdam | 8.1 ms | 825 km | Mapped fibre route |
| Paris | 9.2 ms | 940 km | Mapped fibre route |
| London | 11 ms | 1,155 km | Mapped fibre route |
| Dublin | 16 ms | 1,655 km | Mapped fibre route |
Floors for light in fibre, city centre to city centre; operator fibre adds to this.
Rules and dates
Next dates
- 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
- 31 Dec 2026deadline for existing data centres above 1 MW in Czechia to meet the waste-heat duty
- 15 May 2027EU database and French reports due (every year)
- 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption
Formal refusals and bans since 2025
No area-wide rule recorded for Czechia.
Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.
Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 3 official bodies, checked 23 October 2026: ERÚ (Czech energy regulator), EUR-Lex (Official Journal of the EU), ČEPS.