Step 4 · Sell

See what it sells for

Price, fill and contract terms, as scenarios.

Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Data centres in Czechia

At a glance: Czechia

Pipeline projects
5
2 permitted or being built
Checked 17 Oct 2026
New grid connections
Conditional
červená / oranžová / zelená, in force since 1 Sep 2026. Nationwide, transmission
Checked 23 Oct 2026
Wholesale power price
97€/MWh
Day-ahead, 2025 mean, Czechia
Calendar year 2025
Grid carbon intensity
402g CO₂/kWh
Yearly average, Czechia
Latest full year
Next national rule date
31 Dec 2026
Deadline for existing data centres above 1 MW in Czechia to meet the waste-heat duty
Applies in Czechia
Latency to nearest major hub
4.4 ms
Round trip, Prague to Frankfurt
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 5 data-centre projects in Czechia, and 2 of them are permitted or being built.

Data centres in Czechia in October 2026

The tracker follows 5 data centre projects of 1 MW or more in Czechia, 2 of them permitted or being built. 5 developers are behind them.

Projects by stage

  • Announced 3
  • Under construction 2

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 1
  • Facility, campus or unstated basis 3
  • No capacity published 1

Each capacity is on its own stated basis; never added.

Who is building in Czechia

  • Bluesio Technologies 1
  • Gi21 1
  • MasterDC 1
  • Seznam.cz 1
  • České Radiokomunikace 1

A joint venture counts once per partner. All operators and developers.

What changed

2 milestones in the last 90 days; the newest is from Oct 2026.

Power and grid in Czechia

Conditional

New grid connections are conditional (nationwide, transmission, since 1 Sep 2026). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
402g CO₂/kWh
27th cleanest of 30 countries; 59% renewable or nuclear
Business electricity price, latest full year
233€/MWh
26th cheapest of 26; wholesale is 47% of it
Wholesale power, 2025 average
97€/MWh
15th cheapest of 30
Cooling degree days
33a year
10-year national mean

Annual averages are national, for the latest full year.

Fibre latency from Prague

Round trips from Prague
ToRound trip, minimumPath lengthPath
Vienna2.8 ms286 kmMapped fibre route
Berlin3.1 ms320 kmMapped fibre route
Munich3.5 ms355 kmMapped fibre route
Frankfurt4.4 ms445 kmMapped fibre route
Amsterdam8.1 ms825 kmMapped fibre route
Paris9.2 ms940 kmMapped fibre route
London11 ms1,155 kmMapped fibre route
Dublin16 ms1,655 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 31 Dec 2026deadline for existing data centres above 1 MW in Czechia to meet the waste-heat duty
  3. 15 May 2027EU database and French reports due (every year)
  4. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Czechia.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 3 official bodies, checked 23 October 2026: ERÚ (Czech energy regulator), EUR-Lex (Official Journal of the EU), ČEPS.