Step 4 · Sell

See what it sells for

Price, fill and contract terms, as scenarios.

Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Data centres in Belgium

At a glance: Belgium

Pipeline projects
6
3 permitted or being built
Checked 17 Oct 2026
New grid connections
Conditional
réservations de capacité limitées dans le temps, in force since 29 Jan 2026. Nationwide, transmission
Checked 23 Oct 2026
Wholesale power price
84€/MWh
Day-ahead, 2025 mean, Belgium
Calendar year 2025
Grid carbon intensity
109g CO₂/kWh
Yearly average, Belgium
Latest full year
Next national rule date
31 Mar 2027
Belgium’s Brussels-region report due
Applies in Belgium, every year
Latency to nearest major hub
1.8 ms
Round trip, Brussels to Amsterdam
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 6 data-centre projects in Belgium, and 3 of them are permitted or being built.

Data centres in Belgium in October 2026

The tracker follows 6 data centre projects of 1 MW or more in Belgium, 3 of them permitted or being built. 3 developers are behind them, led by Google (3) and Datacenter United (2).

Projects by stage

  • Announced 3
  • Permitted 1
  • Under construction 2

The whole European pipeline, country by country.

What the capacity figures measure

  • First phase only 1
  • No capacity published 5

Each capacity is on its own stated basis; never added.

Who is building in Belgium

  • Google 3
  • Datacenter United 2
  • Kevlinx Data Centers 1

A joint venture counts once per partner. All operators and developers.

What changed

1 milestone in the last 90 days; the newest is from Aug 2026.

Power and grid in Belgium

Conditional

New grid connections are conditional (nationwide, transmission, since 29 Jan 2026). Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
109g CO₂/kWh
8th cleanest of 30 countries; 80% renewable or nuclear
Business electricity price, latest full year
149€/MWh
11th cheapest of 26; wholesale is 63% of it
Wholesale power, 2025 average
84€/MWh
9th cheapest of 30
Cooling degree days
24a year
10-year national mean

Annual averages are national, for the latest full year.

Fibre latency from Brussels

Round trips from Brussels
ToRound trip, minimumPath lengthPath
Amsterdam1.8 ms181 kmMapped fibre route
Paris2.8 ms290 kmMapped fibre route
London3.5 ms357 kmMapped fibre route
Frankfurt3.5 ms357 kmMapped fibre route
Zurich6.7 ms681 kmMapped fibre route
Munich6.8 ms696 kmMapped fibre route
Berlin7.1 ms720 kmMapped fibre route
Dublin8.7 ms883 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 31 Mar 2027Belgium’s Brussels-region report due (every year)
  3. 15 May 2027EU database and French reports due (every year)
  4. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Belgium.

1 decision on a single site since 2025, not listed here.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 4 official bodies, checked 23 October 2026: CREG (Belgian regulator), EUR-Lex (Official Journal of the EU), Fluvius, ORES.