Data centres in Sweden

Oct 2026: 13 projects in the pipeline in Sweden, 6 permitted or being built.New grid connections congested. Wholesale power €43/MWh in 2025.

Pipeline projects
13
6 permitted or being built
New grid connections
Congested
All kapacitet för uttag är för närvarande tilldelad. Stockholm, transmission
Wholesale power price
43€/MWh
Day-ahead, 2025 mean, Sweden

Plan a site in Sweden

Pipeline movement, last 12 months

10 milestones ·

Dec 2025: 1Jan 2026: 1Feb 2026: 1Jun 2026: 2Aug 2026: 1Sep 2026: 2Oct 2026: 2

99 data centres on record in Sweden

Projects by stage

  • Announced 4
  • In planning 3
  • Permitted 1
  • Contractor appointed 1
  • Under construction 4

European pipeline

Who is building in Sweden

All operators and developers

Capacity by stage

Facility power, all stages
1,600 MW
Facility power, under construction
0 MW
Projects
13

Stated by each project, . Bases are never added together.

Stated MW by stage and capacity basis, and projects by stage
StageIT load, MWFacility power, MWGrid connection, MWProjects
Announced·1,150·4
In planning·150·3
Permitted6300·2
Under construction··84
In service···0

Premium Premium adds the quarterly series and all 13 projects. Frankfurt is open in full with a free account.

Market economics, Stockholm

Premium

Premium adds build cost, rents and power prices for Stockholm. Frankfurt is open in full with a free account.

Construction cost
Premium figure
EUR m per MW
Nov 2025
Business electricity
Premium figure
EUR per MWh
H1 2026
Permitting
Premium figure
months
Sep 2022
Staff cost
Premium figure
EUR k per FTE a year
2020
Guarding, 24/7
Premium figure
EUR k a year
Apr 2026

Create a free accountSee pricing

Operators in Sweden

All operators

What changed

5 milestones since 1 Aug 2026; the newest is from Oct 2026.

Power and grid in Sweden

Congested

New grid connections are congested (Stockholm, transmission). Every country’s grid connections

Over a year, country level

Grid carbon, latest full-year average
35g CO₂/kWh
2nd cleanest of 30 countries; 99% renewable or nuclear
Business electricity price, latest full year
89€/MWh
3rd cheapest of 26; wholesale is 66% of it
Wholesale power, 2025 average
43€/MWh
2nd cheapest of 30

Climate at Stockholm

Hours a year above 27 °C dry-bulb
13h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
0h
worst year 0 h
Hours a year above 20 °C wet-bulb
39h
limit for evaporative cooling

Fibre latency from Stockholm

Round trips from Stockholm
ToRound trip, minimumPath lengthPath
Helsinki3.9 ms396 kmStraight line (no mapped land route)
Oslo4.3 ms438 kmMapped fibre route
Copenhagen5.6 ms573 kmMapped fibre route
Amsterdam12 ms1,261 kmMapped fibre route
Frankfurt13 ms1,292 kmMapped fibre route
London16 ms1,669 kmMapped fibre route
Paris17 ms1,707 kmMapped fibre route
Dublin19 ms1,950 kmMapped fibre route

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 1 Jan 2027proposed entry into force of Sweden’s draft law on cost-benefit analysis and waste heat use for data centres above 1 MW, if it is adopted
  3. 15 May 2027EU database and French reports due (every year)
  4. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Sweden.

Other markets

Sources

Copernicus Climate Change Service (ERA5), EUR-Lex (Official Journal of the EU), Sollefteå kommun, Svenska kraftnät, Timrå kommun, Vattenfall Eldistribution.