Markets and operators: who is building where

The pipeline, the grid, the power, the latency and the rules of a market, and the operators building in it. Counts and dated figures, from the tracker and the official sources.

Plan a site in Paris

Paris data centre market

At a glance: Paris

Pipeline projects
20
9 permitted or being built
Checked 17 Oct 2026
New grid connections
No pause or cap
No rule in force for Paris pauses, rations or conditions them
Checked 23 Oct 2026
Wholesale power price
63€/MWh
Day-ahead, 2025 mean, France
Calendar year 2025
Grid carbon intensity
42g CO₂/kWh
Yearly average, France
Latest full year
Next national rule date
15 May 2027
EU database and French reports due
Applies in France, every year
Latency to nearest major hub
4.0 ms
Round trip, Paris to London
Mapped fibre route, minimum

Data checked

On 17 October 2026 the pipeline tracker lists 20 data-centre projects around Paris, and 9 of them are permitted or being built.

The Paris data centre market in October 2026

The tracker follows 20 data centre projects of 1 MW or more around Paris, 9 of them permitted or being built. 20 developers are behind them, led by Goodman (3), Equinix (2) and Opcore (2).

Projects by stage

  • Announced 1
  • In planning 10
  • Permitted 1
  • Contractor appointed 1
  • Under construction 7

The whole European pipeline, country by country.

What the capacity figures measure

  • IT load 3
  • Facility, campus or unstated basis 9
  • Grid connection 6
  • No capacity published 2

Each capacity is on its own stated basis; never added.

Who is building in Paris

And 10 other developers with one project each. A joint venture counts once per partner. All operators and developers.

Where the data centres are around Paris

  • Argenteuil 1
  • Aubergenville 1
  • Aulnay-sous-Bois 1
  • Bonneuil-sur-Marne 1
  • Dugny 1
  • Fouju 1
  • La Grande-Paroisse 1
  • Le Coudray-Montceaux 1
  • Lisses 1
  • Meudon 1
  • Nozay 1
  • Rungis 1
  • Réau 1
  • Saint-Ouen-l'Aumône 1
  • Trappes 1
  • Tremblay-en-France 1
  • Villebon-sur-Yvette 1
  • Villeneuve-Saint-Georges 1
  • Vélizy-Villacoublay 1
  • Wissous 1

What changed

6 milestones in the last 90 days; the newest is from Oct 2026.

Power and grid for Paris

No pause or cap

No rule in force pauses, rations or conditions new grid connections here. Checked 23 Oct 2026. Every country’s grid connections.

Over a year, country level

Grid carbon, latest full-year average
42g CO₂/kWh
4th cleanest of 30 countries; 95% renewable or nuclear
Business electricity price, latest full year
92€/MWh
4th cheapest of 26; wholesale is 68% of it
Wholesale power, 2025 average
63€/MWh
4th cheapest of 30

Climate at Paris

Hours a year above 27 °C dry-bulb
233h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
40h
worst year 68 h
Hours a year above 20 °C wet-bulb
147h
limit for evaporative cooling

Hourly reanalysis at the city’s grid cell, 2016 to 2025.

Annual averages are national, for the latest full year.

Fibre latency from Paris

Round trips from Paris
ToRound trip, minimumPath lengthPath
Brussels2.8 ms290 kmMapped fibre route
London4.0 ms409 kmMapped fibre route
Amsterdam4.4 ms453 kmMapped fibre route
Frankfurt5.9 ms599 kmMapped fibre route
Zurich5.9 ms601 kmMapped fibre route
Milan8.0 ms817 kmMapped fibre route
Dublin9.1 ms929 kmMapped fibre route

Floors for light in fibre, city centre to city centre; operator fibre adds to this.

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force
FranceAnnual reporting from 500 kW and waste-heat valorisation from 1 MW; an energy reuse factor of at least 0.20 is deemed compliantIn force

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due (every year)
  3. 1 Oct 2027France’s cost-benefit analysis deadline for data centres with permits filed before 1 January 2026
  4. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Paris.

1 decision on a single site since 2025, not listed here.

Decisions from 1 Jan 2025; statuses checked 21 Oct 2026. A market with none recorded is not a low risk market.

Projects of 1 MW or more, announced to under construction, not yet fully operating; a metro includes its region. Capacities are never added, and no project is listed. Grid: new-connection status from the grid connection tracker. Over a year: national averages, latest full year. Latency: light in fibre over the mapped land route, else the straight line. Sources, 5 official bodies, checked 23 October 2026: Copernicus Climate Change Service (ERA5), CRE (French regulator), EUR-Lex (Official Journal of the EU), MRAe Île-de-France, RTE.