Data centres in Poland

Oct 2026: 12 projects in the pipeline in Poland, 2 permitted or being built.New grid connections congested since 30 Sep 2026. Wholesale power €104/MWh in 2025.

Pipeline projects
12
2 permitted or being built
New grid connections
Congested
dostępne moce przyłączeniowe odbiorcze, in force since 30 Sep 2026. Nationwide, transmission
Wholesale power price
104€/MWh
Day-ahead, 2025 mean, Poland

Plan a site in Poland

Pipeline movement, last 12 months

9 milestones ·

Feb 2026: 1Mar 2026: 2Apr 2026: 1May 2026: 1Jul 2026: 1Sep 2026: 3

124 data centres on record in Poland

Projects by stage

  • Announced 9
  • In planning 1
  • Permitted 2

European pipeline

Who is building in Poland

  • Atman 1
  • Beyond.pl 1
  • Centralna Grupa Energetyczna 1
  • Data4 1
  • DL Invest Group 1
  • Greykite European Real Estate Fund I 1
  • Hillwood Polska 1
  • Polcom 1
  • Twenty20 Energy Poland 1
  • WBS Power 1

All operators and developers

Capacity by stage

Facility power, all stages
1,305 MW
Facility power, under construction
0 MW
Projects
12

Stated by each project, . Bases are never added together.

Stated MW by stage and capacity basis, and projects by stage
StageIT load, MWFacility power, MWGrid connection, MWProjects
Announced1431,1055009
In planning·200·1
Permitted···2
Under construction···0
In service···0

Premium Premium adds the quarterly series and all 12 projects. Frankfurt is open in full with a free account.

Market economics, Warsaw

Premium

Premium adds build cost, rents and power prices for Warsaw. Frankfurt is open in full with a free account.

Construction cost
Premium figure
EUR m per MW
Nov 2025
Business electricity
Premium figure
EUR per MWh
H1 2026
Permitting
Premium figure
months
Jul 2023
Property tax
Premium figure
EUR k per MW a year
Nov 2025
Staff cost
Premium figure
EUR k per FTE a year
2024
Guarding, 24/7
Premium figure
EUR k a year
Apr 2026

Create a free accountSee pricing

Operators in Poland

All operators

What changed

3 milestones since 1 Aug 2026; the newest is from Sep 2026.

Power and grid in Poland

Congested

New grid connections are congested (nationwide, transmission, since 30 Sep 2026). Every country’s grid connections

Over a year, country level

Grid carbon, latest full-year average
591g CO₂/kWh
29th cleanest of 30 countries; 31% renewable or nuclear
Business electricity price, latest full year
233€/MWh
25th cheapest of 26; wholesale is 29% of it
Wholesale power, 2025 average
104€/MWh
19th cheapest of 30

Climate at Warsaw

Hours a year above 27 °C dry-bulb
215h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
14h
worst year 27 h
Hours a year above 20 °C wet-bulb
186h
limit for evaporative cooling

Fibre latency from Warsaw

Round trips from Warsaw
ToRound trip, minimumPath lengthPath
Berlin5.6 ms568 kmMapped fibre route
Vienna6.4 ms654 kmMapped fibre route
Prague6.7 ms685 kmMapped fibre route
Frankfurt9.5 ms965 kmMapped fibre route
Amsterdam12 ms1,217 kmMapped fibre route
Paris15 ms1,536 kmMapped fibre route
London16 ms1,624 kmMapped fibre route
Dublin20 ms2,046 kmMapped fibre route

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due (every year)
  3. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

  1. 26 Aug 2026Dobre, Masovia Council removed a data-centre zone from the draft general plan. Standing

1 decision on a single site since 2025, not listed here.

Other markets

Sources

City of Gliwice, Copernicus Climate Change Service (ERA5), Dziennik Ustaw (Polish official journal), EUR-Lex (Official Journal of the EU), PSE.