Data centres in the Netherlands

Oct 2026: 24 projects in the pipeline in the Netherlands, 14 permitted or being built.New grid connections rationed since 8 Apr 2026. Wholesale power €88/MWh in 2025.

Pipeline projects
24
14 permitted or being built
New grid connections
Rationed
maximaal aansluitvermogen datacentrum, in force since 8 Apr 2026. Amsterdam, distribution
Wholesale power price
88€/MWh
Day-ahead, 2025 mean, Netherlands

Plan a site in Amsterdam

Pipeline movement, last 12 months

18 milestones ·

Nov 2025: 1Jan 2026: 1Feb 2026: 1Mar 2026: 2Apr 2026: 3Jun 2026: 1Jul 2026: 3Aug 2026: 3Sep 2026: 2Oct 2026: 1

332 data centres on record in the Netherlands

Projects by stage

  • Announced 2
  • In planning 8
  • Permitted 8
  • Under construction 6

European pipeline

Who is building in the Netherlands

All operators and developers

Capacity by stage

Facility power, all stages
278.5 MW
Facility power, under construction
78 MW
Projects
24

Stated by each project, . Bases are never added together.

Stated MW by stage and capacity basis, and projects by stage
StageIT load, MWFacility power, MWGrid connection, MWProjects
Announced60095·2
In planning·78·8
Permitted·27.51608
Under construction29.478·6
In service···0

Premium Premium adds the quarterly series and all 24 projects. Frankfurt is open in full with a free account.

Market economics, Amsterdam

Premium

Premium adds build cost, rents and power prices for Amsterdam. Frankfurt is open in full with a free account.

Construction cost
Premium figure
EUR m per MW
Sep 2026
Colocation, wholesale
Premium figure
EUR per kW a month
Jun 2026
Business electricity
Premium figure
EUR per MWh
H1 2026
Grid connection wait
Premium figure
years
Aug 2026
Permitting
Premium figure
months
Jan 2024
Staff cost
Premium figure
EUR k per FTE a year
2024
Guarding, 24/7
Premium figure
EUR k a year
Jul 2026

Create a free accountSee pricing

Operators in the Netherlands

All operators

Where the data centres are in the Netherlands

What changed

6 milestones since 1 Aug 2026; the newest is from Oct 2026.

Power and grid in the Netherlands

Rationed

New grid connections are rationed (Amsterdam, distribution, since 8 Apr 2026). Every country’s grid connections

Over a year, country level

Grid carbon, latest full-year average
254g CO₂/kWh
18th cleanest of 30 countries; 54% renewable or nuclear
Business electricity price, latest full year
165€/MWh
16th cheapest of 26; wholesale is 61% of it
Wholesale power, 2025 average
88€/MWh
12th cheapest of 30

Climate at Amsterdam

Hours a year above 27 °C dry-bulb
80h
mean of 2016 to 2025
Hours a year above 32 °C dry-bulb
8h
worst year 24 h
Hours a year above 20 °C wet-bulb
94h
limit for evaporative cooling

Fibre latency from Amsterdam

Round trips from Amsterdam
ToRound trip, minimumPath lengthPath
Brussels1.8 ms181 kmMapped fibre route
Frankfurt3.8 ms392 kmMapped fibre route
London4.0 ms411 kmMapped fibre route
Paris4.4 ms453 kmMapped fibre route
Berlin6.4 ms651 kmMapped fibre route
Zurich7.0 ms715 kmMapped fibre route
Dublin8.1 ms831 kmMapped fibre route

Rules and dates

Rules in force or proposed
WhereRuleStatus
EUReporting duty from 500 kW installed IT power, 7 items and 24 indicators, next report 15 May 2027In force
EUWaste-heat use above 1 MW total rated energy input, unless a cost-benefit assessment shows it is not feasibleIn force
EUCommon rating scheme adopted 21 Sep 2026; in Parliament and Council scrutiny, extended 6 OctAdopted, not in force
NetherlandsNew hyperscale data centres restricted nationally to two designated areasIn force

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 15 May 2027EU database and French reports due (every year)
  3. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

  1. 23 Sep 2026Westland, South Holland Council adopted a ban on new data centres across nearly all of the municipality. Adopted; not yet in force (appeal period to 20 Nov 2026)
  2. 23 Jun 2026Oldambt, Groningen Temporary ban on new data centres on business land while the zoning plan is revised. In force
  3. 26 May 2026Heusden, North Brabant Temporary ban on new data centres, up to 18 months, while the zoning plan is revised. In force
  4. 12 May 2026Zaanstad, near Amsterdam Zoning plan bars new data centres above 2,000 m² floor area and 5 MVA. In force
  5. 11 Jun 2025Amsterdam Zoning plan bars new or larger data centres above 2,000 m² floor area and 5 MVA. In force

Other markets

Sources

ACM (Dutch regulator), Commissie voor de milieueffectrapportage, Copernicus Climate Change Service (ERA5), EUR-Lex (Official Journal of the EU), Gemeente Aalsmeer, Gemeente Amsterdam, Gemeente Diemen, Gemeente Haarlemmermeer, Gemeente Lelystad, Hoogheemraadschap van Rijnland, Liander, Netbeheer Nederland, Officiële bekendmakingen (Dutch official gazette), Omgevingsdienst Noordzeekanaalgebied, Provincie Flevoland, Provincie Groningen, Provincie Noord-Holland, TenneT.