Data centres in Belgium

Oct 2026: 6 projects in the pipeline in Belgium, 3 permitted or being built.New grid connections conditional since 29 Jan 2026. Wholesale power €84/MWh in 2025.

Pipeline projects
6
3 permitted or being built
New grid connections
Conditional
réservations de capacité limitées dans le temps, in force since 29 Jan 2026. Nationwide, transmission
Wholesale power price
84€/MWh
Day-ahead, 2025 mean, Belgium

Pipeline movement, last 24 months

3 milestones ·

Oct 2025: 1Jan 2026: 1Aug 2026: 1

83 data centres on record in Belgium

Projects by stage

  • Announced 3
  • Permitted 1
  • Under construction 2

European pipeline

Who is building in Belgium

  • Google 3
  • Datacenter United 2
  • Kevlinx Data Centers 1

All operators and developers

Capacity by stage

Facility power, all stages
65 MW
Facility power, under construction
0 MW
Projects
6

Stated by each project, . Bases are never added together.

Stated MW by stage and capacity basis, and projects by stage
StageFacility power, MWProjects
Announced653
In planning·0
Permitted·1
Under construction·2
In service·0

Premium Premium adds the quarterly series and all 6 projects. Frankfurt is open in full with a free account.

Operators in Belgium

All operators

What changed

1 milestone since 1 Aug 2026; the newest is from Aug 2026.

Power and grid in Belgium

Conditional

New grid connections are conditional (nationwide, transmission, since 29 Jan 2026). Every country’s grid connections

Over a year, country level

Grid carbon, latest full-year average
109g CO₂/kWh
8th cleanest of 30 countries; 80% renewable or nuclear
Business electricity price, latest full year
149€/MWh
11th cheapest of 26; wholesale is 63% of it
Wholesale power, 2025 average
84€/MWh
9th cheapest of 30
Cooling degree days
24a year
10-year national mean

Fibre latency from Brussels

Round trips from Brussels
ToRound trip, minimumPath lengthPath
Amsterdam1.8 ms181 kmMapped fibre route
Paris2.8 ms290 kmMapped fibre route
London3.5 ms357 kmMapped fibre route
Frankfurt3.5 ms357 kmMapped fibre route
Zurich6.7 ms681 kmMapped fibre route
Munich6.8 ms696 kmMapped fibre route
Berlin7.1 ms720 kmMapped fibre route
Dublin8.7 ms883 kmMapped fibre route

Rules and dates

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 31 Mar 2027Belgium’s Brussels-region report due (every year)
  3. 15 May 2027EU database and French reports due (every year)
  4. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Belgium.

1 decision on a single site since 2025, not listed here.

Other markets

Sources

CREG (Belgian regulator), EUR-Lex (Official Journal of the EU), Fluvius, ORES.