Data centres in Estonia
Oct 2026: 3 projects in the pipeline in Estonia, 1 permitted or being built.Wholesale power €81/MWh in 2025.
Pipeline movement, last 24 months
3 milestones ·
11 data centres on record in Estonia
Projects by stage
Who is building in Estonia
Capacity by stage
- Facility power, all stages
- 280 MW
- Facility power, under construction
- 0 MW
- Projects
- 3
Stated by each project, . Bases are never added together.
| Stage | Facility power, MW | Projects |
|---|---|---|
| Announced | · | 0 |
| In planning | 280 | 2 |
| Permitted | · | 0 |
| Under construction | · | 1 |
| In service | · | 0 |
Premium Premium adds the quarterly series and all 3 projects. Frankfurt is open in full with a free account.
Operators in Estonia
What changed
2 milestones since 1 Aug 2026; the newest is from Sep 2026.
Power and grid in Estonia
Over a year, country level
- Grid carbon, latest full-year average
- 317g CO₂/kWh
- 24th cleanest of 30 countries; 60% renewable or nuclear
- Business electricity price, latest full year
- 159€/MWh
- 15th cheapest of 26; wholesale is 52% of it
- Wholesale power, 2025 average
- 81€/MWh
- 7th cheapest of 30
- Cooling degree days
- 9a year
- 10-year national mean
Rules and dates
Next dates
- 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
- 15 May 2027EU database and French reports due (every year)
- 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption
Formal refusals and bans since 2025
No area-wide rule recorded for Estonia.