Data centres in Czechia

Oct 2026: 5 projects in the pipeline in Czechia, 2 permitted or being built.New grid connections conditional since 1 Sep 2026. Wholesale power €97/MWh in 2025.

Pipeline projects
5
2 permitted or being built
New grid connections
Conditional
červená / oranžová / zelená, in force since 1 Sep 2026. Nationwide, transmission
Wholesale power price
97€/MWh
Day-ahead, 2025 mean, Czechia

Pipeline movement, last 24 months

5 milestones ·

Nov 2025: 3Sep 2026: 1Oct 2026: 1

66 data centres on record in Czechia

Projects by stage

  • Announced 3
  • Under construction 2

European pipeline

Who is building in Czechia

  • Bluesio Technologies 1
  • Gi21 1
  • MasterDC 1
  • Seznam.cz 1
  • České Radiokomunikace 1

All operators and developers

Capacity by stage

Facility power, all stages
69 MW
Facility power, under construction
25 MW
Projects
5

Stated by each project, . Bases are never added together.

Stated MW by stage and capacity basis, and projects by stage
StageFacility power, MWProjects
Announced443
In planning·0
Permitted·0
Under construction252
In service·0

Premium Premium adds the quarterly series and all 5 projects. Frankfurt is open in full with a free account.

Operators in Czechia

All operators

What changed

2 milestones since 1 Aug 2026; the newest is from Oct 2026.

Power and grid in Czechia

Conditional

New grid connections are conditional (nationwide, transmission, since 1 Sep 2026). Every country’s grid connections

Over a year, country level

Grid carbon, latest full-year average
402g CO₂/kWh
27th cleanest of 30 countries; 59% renewable or nuclear
Business electricity price, latest full year
233€/MWh
26th cheapest of 26; wholesale is 47% of it
Wholesale power, 2025 average
97€/MWh
15th cheapest of 30
Cooling degree days
33a year
10-year national mean

Fibre latency from Prague

Round trips from Prague
ToRound trip, minimumPath lengthPath
Vienna2.8 ms286 kmMapped fibre route
Berlin3.1 ms320 kmMapped fibre route
Munich3.5 ms355 kmMapped fibre route
Frankfurt4.4 ms445 kmMapped fibre route
Amsterdam8.1 ms825 kmMapped fibre route
Paris9.2 ms940 kmMapped fibre route
London11 ms1,155 kmMapped fibre route
Dublin16 ms1,655 kmMapped fibre route

Rules and dates

Next dates

  1. 14 Dec 2026the EU Commission’s minimum performance standards consultation and call for evidence closes
  2. 31 Dec 2026deadline for existing data centres above 1 MW in Czechia to meet the waste-heat duty
  3. 15 May 2027EU database and French reports due (every year)
  4. 11 Oct 2027EU deadline under Article 11 of the Energy Efficiency Directive for a certified energy management system at enterprises above 85 TJ (23.6 GWh) of annual energy consumption

Formal refusals and bans since 2025

No area-wide rule recorded for Czechia.

Other markets

Sources

ERÚ (Czech energy regulator), EUR-Lex (Official Journal of the EU), ČEPS.